DWC 3.1.0 bug: invalid estimation time with sequenta printing



  • I decided to try new functionality of RRF 3.1: cancel individual objects from the job
    to do so, in Slic3R-PE i have selected "complete individual objects" and "label objects"

    once printer finished first item and started 2nd one - layer time and slicer time became ZERO, that is not correct at all...

    29972971-3e56-4146-b1a4-2d8421d98de0-изображение.png

    1011961d-e29d-41d8-a7c5-86dac6095868-изображение.png


Log in to reply